Update on the Living Stones project is as follows.-
Faculty
Application
No 0818. granted 12th January 2010 and confirmation
of available finance acknowledged by7 the chancellors office on
20th January 2010..
Tender Process
Tenders received from 4 main
contractors and 2 joinery companies. Prices range from £60855 to
£124638 excluding Joinery. Joinery Tenders range from £12085 to
£17027. (Prices exc VAT)
Tenders were reviewed in detail
with our architect on 16th December 2009 and
financial report obtained for lowest price contractor.
Minor variations from ‘interest
group’ meeting and building control are being costed to achieve
firm fixed price for full scope of work before contract award.
PCC approvals
PCC meeting was held on 19th
January 2010.
a)
The PCC authorised the appointment of
Hare Builders to undertake the phase 2 works for a maximum sum
of £80000 + VAT including joinery subject to building regulation
consent. Work to commence in March and complete by end May 2010.
b)
The PCC authorised the purchase of 50
folding chairs of the design recently trialled for a sum not to
exceed £3000.
Building Regulations
Application for building reg’s
consent submitted and acknowledged 21s December
09.(Reg No 11869/09/FP) Feedback received re emergency lighting,
fire alarms, and colour schemes for the sight impaired.
Response is in progress.
Grant Funding Applications
National Churches Trust
application was waiting on the Faculty being granted. This will
now be progressed.
A possible opportunity to
approach the Bridge Wardens Trust for Organ replacement grant
funding is being investigated. Closing date is 2nd
April 1010
Target dates
Building Reg’s consent Jan 2010.
Contract award early Feb.
Ground work commencing Mar 2010
followed by internal works for which the scope is drainage,
WC, flower arranging area, crèche, welcoming area, refreshment
facilities and South door disabled access.
Phases
Phase 1 Stonework repair –
completed.
Phase 2 Drainage, WC, flower
arranging, refreshment & welcoming area, South door disabled
access – work due to start imminently.
Phase 3 Tower & West door
entrance plus damaged pipe organ removal.
Phase 4 Worship and music area
Phase 5 Heating survey /
replacement?
Next steps
Finalise building regulation
consent
Finalise colour schemes
Develop disposal options for
pipe organ and develop designs for West door entrance and base
of tower.
Develop designs for music and
worship areas. Identify replacement organ.
Survey heating requirements and
options